Gloucester Docks silt: £4m dredging under way, but no reopening date

15 hrs ago

Image of Gloucester docks silt dredging

Gloucester Docks is shut to boats while a large dredging job clears silt that built up over the summer. The Canal & River Trust, which manages the Gloucester and Sharpness Canal, began work in early October. It says it aims to have most of the silt removed in time for the boating season in early 2027.

Why the docks silted up

Water has to be pumped from the River Severn to keep the docks working. During long dry spells, the river runs low, so the pumps draw water from nearer the riverbed, where there is more sediment. Silt levels rose so high this summer that water depths fell below what boats need, leaving some trapped and forcing the docks to close.

Some people have pointed to water being pumped from the canal to supply Bristol. Bristol Water says the canal’s operator is responsible for managing silt and that it is working with the trust to reduce sediment transfer.

What the dredging involves

The trust says the work will cost about half of its annual dredging budget. Before the dredger could reach the docks basin, it first had to clear its own channel past Llanthony Swing Bridge, because river levels were so low. The removed silt will be treated and spread on farmland.

The trust has not given a final reopening date. It says the work depends on how quickly the silt can be moved, and that the team is working more efficiently as the job goes on. It expects the work to run into the winter. It has not said when tall ships will be able to return. Its first aim is to reopen the docks to ordinary boat traffic.

What it means for businesses and boaters

Traders at the docks say the closure has hit trade hard. One café owner says summer takings have been as weak as January, because boats cannot reach the docks. The local MP, Alex McIntyre, says dredging is only a short-term fix and wants action to stop the silt entering the system, such as better filtration.

The docks will mark their 200th anniversary in 2027, so there is pressure to have them working before then.

Practical information

  • Gloucester Docks is closed to boats while dredging continues. There is no confirmed reopening date.
  • The dredging is expected to continue into the winter, and the trust says the early 2027 boating season is the target for most of the silt to be removed.
  • For updates on the dredging and any reopening, check the Canal & River Trust website at https://canalrivertrust.org.uk/. It is the operator of the canal and the source of any official changes to navigation.
  • Tall ships are not expected to return until the trust has assessed what more is needed for larger vessels.